== Work plan ==
 
== Work plan ==
 +
 +
The following plan reflects the complete plan of activities for the definition of the Integration and Interoperability Framework.
 +
 +
* '''Activity (Re)Planning and Methodology Definition (M2)''': According to the approach of a two-directional definition and development of interoperability framework, the activity  has to be re-planned to encompass RTD WPs activity.
 +
* '''Framework Conceptualization and Work Group Definition (M3)''': Conceptualization of framework and its elements and assignment of tasks for analysis to working groups.
 +
* '''Framework Principles Definition (M4)''': Definition of principles governing various framework elements.
 +
* '''RTD WP Assessment #1 (M10)''': Assessment of developments in other RTD WPs for refining the initial concepts.
 +
* '''Framework Definition (M12)''': Formalization of framework definition in terms procedures and technologies, as a specialization of principles laid out in initial definition.
 +
* '''RTD WP Assessment #2 (M16)''': Assessment of developments in other RTD WPs for extending and specializing the previous concepts.
 +
* '''Framework Toolkit Definition (M18)''': Definition of technologies that form integral part of the framework.
 +
* '''RTD WP Assessment #3 (M24)''': Assessment of developments in other RTD WPs for finalizing the framework.
 +
* '''Framework Definition Finalization (M26)''': Finalization of framework definition.

Revision as of 18:49, 10 April 2012

The goal of this activity is to lay the foundations towards Integration and Interoperability for supporting the exploitation of the gCube-based Data e-Infrastructure facilities by other neighbouring and external ones. These activities include the definition of the Integration and Interoperability Frameworks of gCube and the establishment of a methodology for their evolution.

Methodology

A specific methodology has been defined to drive the whole activity (Methodology).

Such methodology is based on a number of Working Groups.

Integration and Interoperability Framework Definition

Work plan

The following plan reflects the complete plan of activities for the definition of the Integration and Interoperability Framework.

  • Activity (Re)Planning and Methodology Definition (M2): According to the approach of a two-directional definition and development of interoperability framework, the activity has to be re-planned to encompass RTD WPs activity.
  • Framework Conceptualization and Work Group Definition (M3): Conceptualization of framework and its elements and assignment of tasks for analysis to working groups.
  • Framework Principles Definition (M4): Definition of principles governing various framework elements.
  • RTD WP Assessment #1 (M10): Assessment of developments in other RTD WPs for refining the initial concepts.
  • Framework Definition (M12): Formalization of framework definition in terms procedures and technologies, as a specialization of principles laid out in initial definition.
  • RTD WP Assessment #2 (M16): Assessment of developments in other RTD WPs for extending and specializing the previous concepts.
  • Framework Toolkit Definition (M18): Definition of technologies that form integral part of the framework.
  • RTD WP Assessment #3 (M24): Assessment of developments in other RTD WPs for finalizing the framework.
  • Framework Definition Finalization (M26): Finalization of framework definition.